Page 40 - Shipyards
P. 40
PIPING WORKS
Charges in U.S. Dollar
Dia Elbow Welding of
Inch Renewal / m /bend Tee flange & nipple Clamps Joints bolts per
run or one unit
per one pipe
bush
Up to 0.5 20 8 23 8 18 14
0.75 22 9 25 9 18 14
1 23 10 28 10 19 23
1.25 25 16 36 11 21 23
1.5 45 23 41 13 26 23
2 50 25 50 16 31 26
2.5 55 28 55 18 34 28
3 65 31 66 23 36 33
4 69 48 83 30 39 33
5 121 73 124 49 49 36
6 138 93 179 63 59 118
8 193 220 275 78 66 118
10 440 316 550 131 75 120
12 485 364 605 218 83 120
Above12 Per agreements
Notes :
(١) For intermediate sizes the next higher size will be applied .
(٢) Copper pipes extra charge 75%.
(٣) Min length is based on one meter / Pipe.
(٤) Pipes in engine room, pump room, double bottom, cargo tanks, extra charge 20%.
(٥) Removal and refit on board 40% of renewal.
(٦) Flanges to be calculated as 10 U.S.D per one inch of pipe size .
(٧) High pressure pipes as per agreement.
(٨) Removal for burning and testing and refit 60% of renewal.
(٩) Charges based on renewal of pipes up to schedule 40.
(١٠) In case of using any owner supply materials or reuse any part, charges will be reduced by 40% for
the concerning parts.
(١١) Renewal of branch without tee connection will be considered as normal pipe with min. length of 0.5
meter.
(١٢) Staging, clamp, insulation removals for access are excluded.
39