Page 31 - Shipyards
P. 31

ANCHOR, CHAIN AND

                                        CHAIN LOCKERS WORKS

          a)  Range anchor cables & reboarding.
          b)  Sand blasting & painting.

          c)  Calibration of both chains and report readings.

          d)  Link pins fasting by welding per each ( min. 10 nos).
          e)  Disconnect end at chain lockers, exchange first shot and reconnect.

          f)  Chain locker cleaning & painting (Two Coats).


                                                                  Works
                 Gross Tonnages         (a)        (b)         (c)        (d)         (e)        (f)
                                      U.S.D       U.S.D      U.S.D      U.S.D       U.S.D      U.S.D
                 Up to          1000   175         175         65          5         325         175
                             2 000     250         250         80          6         400         225
                             5 000     295         315         95          8         475         265
                            10 000     340         350        105          9         600         295
                            15 000     435         370        115         10         700         315
                            20 000     490         390        120         13         800         370
                            30 000     540         430        130         15         925         410
                  Above     30 000     640         465        140         18         1000        450

          Notes :


                    (١) Price based on one anchor.
                    (٢) Paints are owners supply.

                    (٣) Removal from dock bottom, repair of shackles and anchor will be charged extra.
                    (٤) Removal of grating and floor plates for chain locker are excluded.

                    (٥) Removal of mud from chain locker additional 20 U.S.D. / per ton.
                    (٦) Pumping out existing water from chain lockers if required U.S.D. 5 / per ton.

                              Pumping connection & disconnection U.S.D. 190.















                                                            30
   26   27   28   29   30   31   32   33   34   35   36